Tuesday, 18 March 2014
Polish Transmission System - information
This article aims to introduce the readers to the
Polish Transmission System and provide reliable information about the Polish
TSO called Polskie Sieci Elektoenergetyczne /PSE/ (eng.: Polish Electric
Network).
Poland,
like many other European countries (for example Switzerland or Italy) has one
transmission system operator (TSO) – PSE [ Polskie Sieci Elektroenergetyczne –
Polish Electric Network ]. PSE is responsible for total of 245 lines with a overall length of 13 445 km, including:
◦ 1 line of 750 kV with a length of 114 km,
◦ 77 lines of 400 kV with a total length of 5 383 km,
◦ 167 lines with a voltage of 220 kV with a total length of 7 948 km,
• 101 station high voltage (LV)
• and seabed cable of 450 kV connecting Poland and Sweden, with a total length of 254 km.
◦ 1 line of 750 kV with a length of 114 km,
◦ 77 lines of 400 kV with a total length of 5 383 km,
◦ 167 lines with a voltage of 220 kV with a total length of 7 948 km,
• 101 station high voltage (LV)
• and seabed cable of 450 kV connecting Poland and Sweden, with a total length of 254 km.
Based on the Polish Energy Law, PSE has
certain responsibilities regarding the operation and maintenance of the
transmission system. To describe it shortly, it can be said that Polish TSO
needs to ensure smooth functioning of the grid, ensure short and long-term
security of its function and plan and perform operation, maintenance and eventual
repairs that need to take place. If we would like to look at what is translates
into in more detail, we can say that PSE needs to:
-
Ensure the security and functionality of
the transmission grid of high and medium voltage, as well as of a low voltage
(110 kV) in a form of co-operation with distribution companies
-
Operate, maintain and overhaul the
transmission grid, all ancillary installations and machinery enabling the
connection with other TSOs, in a manner that guarantees reliability of the
whole system
-
Purchase the necessary services that enable
correct functioning of the system
-
Elaborate the emergency plan that describes
the behavior of TSO in case of significant interference of the system, as well
as the action TSO has to take in order of restoring
It is important to point out that PSE is
the body responsible to balancing of electricity in Poland. As the electricity
cannot be stored (there is the need of the constant in – out ratio ), the
electricity that is produced by the power plants and the electricity that is
required by final users needs to be equal. The unbalance of the system might
happen due to many reasons such as rapid incapacity of the power plant to
produce scheduled amount of electricity but also miscalculation or not
profitable production due to the market condition. Since the party which causes
the unbalance is being penalized (the price mechanism of unbalancing will be
described in another post), companies do their best in order to ensure the
reliability of the schedules.
In some countries, common method to avoid
unbalancing is so-called ‘Balance Group Management’ (for example, in Germany
and Switzerland). It is a system that allocates power plants that belong to
particular company into one pool and enables the firm to manage its balancing
individually. The example below illustrates how the balance group works.
Look at the example. If the company owns
three power plants, there needs to be a scheduling of production for each of
them separately. We see that due to different circumstances, some power plants
cannot deliver the electricity that they planned to produce. In order to avoid
fee from the system operator who would need to buy that electricity to make
sure there is correct delivery, the power plants balance each other. Power
plant 1 and 2 produce less than they planned and plant 3 has capacity that
enables it to produce more – consequently, that power plant produces enough
electricity to balance the saldo.
In Poland, such system does not exist – it is
standard balancing mechanism that imposes the responsibility of balanced grid
on the transmission system operator. In order to ensure the balance in the
transmission network, PSE is buying lacking energy from the power plant that
can provide such production. In that case, the power plant that produces is
receiving additional remuneration. The illustration presents the mechanism.
_____
Picture used is the logo of PSE.
Subscribe to:
Post Comments
(
Atom
)
No comments :
Post a Comment
This blog is a place where people show each other respect and discuss in reverent manner. Please, keep that in mind while posting your comment